TECEdrainline – attractive without airs and graces

TECEdrainline – Assembly

The classic composite seal, optimally solved

TECEdrainline in Verbund mit den Seal System Abdichtungsprodukten

Safe installation in the composite seal - with the sealing classic from the Seal System range.

The Seal System sealing tape included in the delivery means that you have one less thing to worry about during installation: thanks to Seal System, you always have absolute security with regard to the compatibility of the composite sealing products with the Seal System sealing tapes and the TECEdrainline shower channels.

The installation of the proven classic is even easier with the optionally available mounting feet, which make it even easier to place and align the channel.

The installation steps

Schritt 1 bei der Montage der Duschrinne TECEdrainline
1 TECEdrainline with stainless steel flange and Seal System sealing tape
2 TECEdrainline drain
3 TECEdrainline assembly feet
4 Edge insulation strips for sound insulation
5 Drainbase sound insulation mat for sound-proofing

Step 1: Before the shower channel is inserted, the shower area is expertly prepared by installing lateral edge insulation strips and a sound insulation mat for impact sound insulation. Now the channel is positioned in the space, aligned and connected. The height of the channel is also easy to adjust thanks to the optionally available assembly feet.

Schritt 2 der Montage der Duschrinne TECEdrainline

Step 2: The screed is installed with a gradient of 1 to 2% to the channel to ensure optimum drainage.

Schritt 3 der Montage der Duschrinne TECEdrainline

Step 3: The Seal System sealing tape is glued on in such a way that it overlaps with the shower channel flange and the screed.

Schritt 4 der Montage der Duschrinne TECEdrainline

Step 4: Afterwards, the first layer of the composite seal is applied.

Schritt 5 der Montage der Duschrinne TECEdrainline

Step 5: Now the composite seal can be completely applied.

Schritt 6 der Montage der Duschrinne TECEdrainline

Step 6: After tiling and grouting, the cover is inserted into the channel body. This concludes the assembly. To enable thorough cleaning, the cover can also be removed any time after assembly and replaced again.